What does the red number on the right side of each project or task signify ?
1 Answer
Answer: The difference between the allocated hours and the hours spent on the project
Explanation:
In Odoo 18, when you view tasks or projects (especially in the Kanban or list views), you may see a red number on the right-hand side. This number shows how much the task or project is deviating from its planned time budget. It is calculated as:
Allocated Hours – Hours Spent (from timesheets)
If the result is positive, it means there is still time remaining within the allocated hours.
If the result is negative, it means more time has been spent than was planned — this is why the number appears in red, to highlight a time overrun.
This helps project managers and team members track time efficiency and quickly identify tasks or projects that are exceeding their estimated effort.